To get data into linked graphics it is necessary to synchronize the data. The synchronizing process copies data from the datasource into all linked graphics and places it in the custom properties of linked graphics.

To Synchronize Data:

  1. Click the Synchronize Data button on toolbar to run synchronizing process.
    Image Modified
  2. Verify that the data has been synchronized by opening the properties of a graphic that is linked and going to the Custom page.
    Image Modified

To Remove Links from Selected Graphics:

  1. Select the graphic/s you wish to de-link.
  2. In the DataSources tree select the link template you wish to de-link from the graphic/s.
    Image Modified
  3. Right-click and select Delete Links(Sel).
    Image Modified
  4. Synchronize the data.
  5. The links and data have been removed.

...

  1. In the DataSources tree select the link template you wish to de-link.
    Image Modified
  2. Right-click and select Delete All Links.
    Image Modified
  3. Synchronize the data.
  4. The links and data have been removed.

...

  1. In the table view, in the lower frame of the palette, click on the record.
  2. Right-click and select Find Graphics.
    Image Modified
  3. All graphics that are linked with current row will be selected.

...

  1. Select a graphic.
  2. Click the View linked records in dataview button on palette's toolbar.
    Image Modified
  3. All records which are linked to the selected object will be highlighted in the table view.
    Image Modified